Updates:

  • Extended for 7 months (January to July 2020)
  • Submitted monthly report for December 2019
  • Implementation of RP is going on smoothly

Akhaura Agartala Dual Gauge Railway Link (Bangladesh Portion) project

Assignment Name:

Construction of Akhaura Agartala Dual Gauge Railway Link (Bangladesh Portion) project

Name of Client:

Bangladesh Railway


Country:

Bangladesh

Assignment Location within country:

Akhaura Upazila of Brahmanbaria District


Start Date (Month/Year):

December 2018

Completion Date (Month/Year):

July 2020


Duration of Assignment (Months):

12 Months

Total No. of staff-month of the assignment:

180


Name of Joint Venture Consultants, if any:

N/A

No. of Staff-Months of Key Professional Staff provided by Joint Venture /Associated Consultants:

0


Name of Senior Staff (Team Leader, Resettlement Specialist/Land Acquisition Specialist/MIS Specialist/Area Manager)Involved and Functions Performed:

Kh. Khairul Matin: Team Leader(Resettlement Specialist), Khandaker Mahabub Alam: Land Acquisition Specialist, Abdul Jabber Jufry: MIS Specialist, Md. Saiful Islam: Area Manager


Narrative Description of Project:

The project is undertaken by Bangladesh Railway for Construction of Akhaura Agartala Dual Gauge Railway Link in Bangladesh Portion. Here Knowledge Management Consultants (KMC) Ltd is engaged by Bangladesh Railway for implementation of Resettlement Plan of the Proposed Dual Gauge Railway Link.


Detailed Description of Actual Services Provided by our Staff: