Coastal Embankment Improvement Project Phase-1 (CEIP-1)

Assignment Name: Preparation of Resettlement Action Plan (RAP), Land Acquisition Plan (LAP), Social Impact Assessment (SIA) and Implementation of the Resettlement Action Plan (RAP) for Coastal Embankment Improvement Project Phase-1 (CEIP-1).

Country: Bangladesh

Assignment Location within country: Khulna, Satkhira, Bagerhat, Pirojpur, Jhalokathi, Borguna & Patuakhali District.

Duration of assignment (months): 60

Name of Client: Dev Consultants Ltd.

Total No. of staff-month of the assignment : 2247

Start Date

 (Month/Year): March-2015

Completion Date

(Month/Year): February-2020

Name of Joint Venture /Associated Consultants, if any: N/A

No. of Staff-Months of Key Professional Staff provided by Joint Venture /Associated Consultants: 0

Name of Senior Staff (Project Director /Coordinator, Team Leader) Involved and Functions Performed:

Kamal Uddin Ahmed Chowdhury

:

Team Leader / Resettlement Specialist

Zahurul Islam

:

Deputy Team Leader

Marufuzzaman

:

MIS Specialist

Detailed Narrative Description of Project:

Bangladesh Water Development Board has recently undertaken theproject: “Coastal Embankment Improvement Project Phase-1 (CEIP-I)”.This project is divided into three packages; Package 1, 2 & 3. Assignment includes LAP & RAP preparation for package 2 and 3 and RAP Implementation package 1, 2 & 3) in 17 polders under 13 Upazilas under 7 districts Khulna, Satkhira, Bagerhat, Pirojpur, Jhalikathi, Borguna&Patuakhali District. Aim of the project is to strengthen construction of retired embankment (618 km), drainage sluice and flashing inlets, etc. Under this project, KMC Ltd. is working as sub-consultant to DevCon to prepare Resettlement Action Plan (RAP), Land Acquisition Plan (LAP), Social Impact Assessment (SIA) and Implementation of the Resettlement Action Plan (RAP).

Detailed Description of Actual Services Provided by your Staff:

- Socio Economic Survey

- Conducting Land survey

- Conducting census and IOL survey and updating information

- Video Filming

- Preparation of Land Acquisition Plan

- Preparation of Resettlement Action Plans

- Indigenous People’s Plan

- Participatory Rapid Assessment/Rapid Rural Assessment

- Property Valuation survey

- Preparation of individual entitlement

- Consultation meeting and FGDS

- Payment of compensation and resettlement benefits to titled and non-titled EPs

- Relocation and resettlement of the HHs