Assignment Name: Environmental Impact Assessment and Approval of Environmental Clearance Certificate and Preparation of Resettlement Action Plan (RAP) for Construction of Akhaura-Agartala Dual Gauge Railway Link (Bangladesh portion) |
|||||
Country: Bangladesh Assignment Location within country: B. Baria |
Duration of assignment (months): 3 |
||||
Name of Client: IRCON Consultants, India |
No. of staff-months : 07 |
||||
Start Date (Month/Year): November 2017 |
Completion Date (Month/Year): January-2018 |
||||
Name of Joint Venture Consultants, if any: N/A |
No. of Staff-Months of Key Professional Staff provided by Joint Venture Consultants: 0 |
||||
Name of Senior Staff (Project Director /Coordinator, Team Leader) Involved and Functions Performed: |
|||||
Ahmed-al-Farouq |
: |
Team Leader (Environment Specialist) |
|||
Nasid Khadem |
: |
Environmental expert |
|||
Kh.Khairul Matin |
: |
Resettlement Specialist |
|||
Abdul Jabber Jufry |
: |
MIS Specialist |
|||
Detailed Narrative Description of Project: Bangladesh Railway has recently undertaken the project of conducting Environmental Impact Assessment and Approval of Environmental Clearance Certificate and Preparation of Resettlement Action Plan (RAP) for Construction of Akhaura-Agartala Dual Gauge Railway Link (Bangladesh portion). The specific work includes Environmental Impact Assessment (EIA), Environment Management Plan (EMP) and preparation of Resettlement Action Plan (RAP. |
|||||
Detailed Description of Actual Services Provided by your Staff: - Census & socioeconomic survey of affected persons, households and communities - Conduct focus group discussion & consultation meetings - Video filming of the traffic scenario during rain operation at all level of crossing - Environmental Impact Assessment - Preparation of Resettlement Action Plan |