Land acquisition & resettlement survey and preparation of Land Acquisition plan (LAP) & Resettlement Action Plan (RAP) for Muktapur Bridge Approach road project
Bangladesh University of Engineering and Technology (BUET)
Bangladesh
Muktapur, Narayangonj
November 2017
January 2018
3
24
N/A
0
This is a project of Bangladesh Bridge Authority (BBA) and financed by GOB where KMC is working as sub consultants to Bangladesh University of Engineering and Technology (BUET). Under this project KMC is assigned to conduct Topographical survey, Land acquisition & resettlement survey and preparation of Land acquisition plan (LAP) and Resettlement Action Plan (RAP.