Updates:

  • Submitted draft Land Acquisition Plan, Resettlement Plan, and Topographic survey reports

Muktapur Bridge Approach Road

Assignment Name:

Land acquisition & resettlement survey and preparation of Land Acquisition plan (LAP) & Resettlement Action Plan (RAP) for Muktapur Bridge Approach road project

Name of Client:

Bangladesh University of Engineering and Technology (BUET)


Country:

Bangladesh

Assignment Location within country:

Muktapur, Narayangonj


Start Date (Month/Year):

November 2017

Completion Date (Month/Year):

January 2018


Duration of Assignment (Months):

3

Total No. of staff-month of the assignment:

24


Name of Joint Venture Consultants, if any:

N/A

No. of Staff-Months of Key Professional Staff provided by Joint Venture /Associated Consultants:

0


Name of Senior Staff (Project Director /Coordinator, Team Leader) Involved and Functions Performed:


Narrative Description of Project:

This is a project of Bangladesh Bridge Authority (BBA) and financed by GOB where KMC is working as sub consultants to Bangladesh University of Engineering and Technology (BUET). Under this project KMC is assigned to conduct Topographical survey, Land acquisition & resettlement survey and preparation of Land acquisition plan (LAP) and Resettlement Action Plan (RAP.


Detailed Description of Actual Services Provided by our Staff: