Assignment Name: Preparation and Implementation of Resettlement Action Plan (RAP) for Padma-Jashaldia Water Treatment Plant Project |
||||||
Country: Bangladesh Assignment Location within country: Dhaka &Munshiganj District |
Duration of assignment (months): 36 |
|||||
Name of Client: Dhaka Water Supply and Sewerage Authority (DWASA) (KMC works as sub-consultant to IWM) |
Total No. of staff-month of the assignment : 100 |
|||||
Start Date (Month/Year): January-2014 |
Completion Date (Month/Year): December-2018 |
|||||
Name of Joint Venture /Associated Consultants, if any: N/A |
No. of Staff-Months of Key Professional Staff provided by Joint Venture /Associated Consultants: 0 |
|||||
Name of Senior Staff (Project Director /Coordinator, Team Leader) Involved and Functions Performed: |
||||||
Kh. Khairul Matin |
: |
Team Leader |
||||
Shariful Islam |
: |
Resettlement Expert |
||||
Md. Zahurul Islam |
: |
Field Coordinator |
||||
Narrative Description of Project: Dhaka Water Supply and Sewerage Authority (DWASA) have recently under taken the project: “Padma (Jashaldia) Water Treatment Plant Project (Phase-1)”. Under the project, a water treatment plant will be set up at Jashaldia (Louhajang Upazila) of Munshiganj district and the treated water of the Padma will be piped to Dhaka city. Here KMC works as sub-consultant to IWM. The main consultant IWM has employed KMC Ltd. to conduct the activities of Preparation and Implementation of Resettlement Action Plan (RAP). |
||||||
Description of Actual Services Provided by your Staff: - Conducting census , Socio-economic survey and inventory of losses - Consultation meetings - Participatory Rapid Assessment - Video filming - Data entry and table generation for RAP preparation - Prepared Resettlement Policy Framework ( RPF) - Resettlement Action Plan (RAP) - Photography of EPs, ID card preparation and distribution - Implementation of Resettlement Action Plan (RAP). |