Power Transmission Network in Eastern Region Project Under Power Grid Company of Bangladesh (PGCB) Ltd. (Package No. S -107)

Assignment Name: Preparation of Resettlement Action Plan (RAP) for Enhancement and Strengthening of Power Transmission Network in Eastern Region Project Under Power Grid Company of Bangladesh (PGCB) Ltd. (Package No. S -107)

Country: Bangladesh

Location within country: Comilla, Feni, Chandpur, Noakhali, etc.

Duration of assignment (months): 03

Name of Client: Power Grid Company of Bangladesh (PGCB) Ltd.

Total No. of Staff-month of the assignment :24.2

Start Date (Month/Year):

January-2017

Completion Date (Month/Year):

October-2017

Name of Joint Venture/ Associated Consultants, if any: N/A

No. of Staff-Months of Professional Staff provided by Joint Venture/ Associated Consultants: N/A

Name of Senior Staff (Project Director /Coordinator, Team Leader) Involved and Functions Performed:

Team Leader

:

Kh. KhairulMatin

MIS Expert

:

Abdul Jabber Jufry

Field Coordinator

:

Md. Zahrul Islam

Narrative Description of Project:

The project is for enhancement and strengthening of Power Transmission Network in Eastern Region of Bangladesh. With regard to the grid enhancement and strengthening works, the project scope includes thirteen (13) GIS substations. Also, land will have to be acquired for constructing new sub-stations. Based on the findings of the SIA, Resettlement Action Plans (RAP) for sub-stations and transmission lines will have to be prepared in compliance with the World Bank's Policy on Involuntary Resettlement (OP 4.12) and relevant Government of Bangladesh (GoB) laws and policies. KMC conducted census and IOL survey, socioeconomic survey, consultation meetings, property valuation survey and prepared Socioeconomic Survey report, Market survey report and Resettlement Action Plan (RAP).

Description of Actual Services Provided by your Staff

- census & socioeconomic survey

- market survey

- focus group & consultation meetings

- video filming of the structure

- preparation & distribution of 10 cards

- data generation, report preparation

- Market survey

- Land Acquisition Plan preparation

- preparation of Resettlement Action Plan