Assignment Name: Preparation of Land Acquisition Proposal (LAP) for Saidabad Water Treatment Plant Project (Phase 3) |
|||||
Country: Bangladesh Assignment Location within country: Narayangonj& Dhaka district |
Duration of assignment (months): 02 |
||||
Name of Client: Dhaka Water Supply and Sewerage Authority (DWASA) |
Total No. of staff-month of the assignment : 05 |
||||
Start Date (Month/Year): June-2015 |
Completion Date (Month/Year): July-2015 |
||||
Name of Joint Venture /Associated Consultants, if any: N/A |
No. of Staff-Months of Key Professional Staff provided by Joint Venture /Associated Consultants: 0 |
||||
Name of Senior Staff (Project Director /Coordinator, Team Leader) Involved and Functions Performed: |
|||||
Mst. Afrina Akhter |
: |
CAD & LA Expert |
|||
Md. Saker Miah |
: |
Jr. CAD Operator |
|||
Anayetullah |
: |
Surveyor |
|||
Narrative Description of Project: Dhaka Water Supply and Sewerage Authority (DWASA) have recently under taken the project: “Saidabad Water Treatment Plant Project (Phase-III)”. Under the project, a water treatment plant will be set up at Char Safi khamouza to HariaMouza of Sonargoanupazila (Narayanganj district) and MatuailMouza of Demra Thana (Dhaka district) and the treated water of the Meghna river will be piped to Dhaka city. Under this project, KMC Ltd. conducted land acquisition survey, collected Mouza Maps, prepared plot schedule and prepared Land Acquisition Proposal (LAP). |
|||||
Description of Actual Services Provided by your Staff: - Conducted field verification Survey of the proposed alignment and - Collected secondary documents including cadastral maps, khatians. - Preparation of Land Scheduling - Preparation of Land Acquisition Proposal (LAP) |